WPTU TICKER

Ship to Shore Crane Nos. 48-55 – Complete: 50% – Completion Date: December, 2023

3 MIN READ

Post image

August 1, 2022 update: 50 percent complete

Design, fabrication, delivery and commissioning of eight (8) ship to shore gantry cranes for Garden City Terminal. Two (2) of the cranes will have a lift height of 152 feet and be placed at the end of Container Berth No. 9. The other six (6) cranes will have a lift height of 165 feet (the largest at the GPA) and be placed at the newly realigned Container Berth 1.

April 6, 2022 update: 30 percent complete

Design, fabrication, delivery and commissioning of eight (8) ship to shore gantry cranes for Garden City Terminal. Two (2) of the cranes will have a lift height of 152 feet and be placed at the end of Container Berth No. 9. The other six (6) cranes will have a lift height of 165 feet (the largest at the GPA) and be placed at the newly realigned Container Berth 1.

 


December 17, 2021 update: 15 percent complete